Project milestones 

January 2016 

Project manager appointed 

February 2016 

Community consultation commenced

March 2016 

Preliminary site analysis

April - June 2016  

Community Consultation Workshops

June 2016 

Council Budget 2016-17 to be adopted - funding for design

July 2016

Design framework produced

 

Aug - Sep 2016  

Tender Process

Oct - Feb 2017

Site analysis and sketch design

Mar - Jun 2017

Preliminary Concept Design

Sept 2017 

Concept Design Development

 Oct 2017

 Public Exhibition of Concept Design

 Nov - Dec 2017

 Stage 1 Documentation

2018

Construction - Stage 1

2018-22

Ongoing implementation – 5 year program